# Delay Cost and Acceleration Break-Even Calculator

> What a week of delay costs once damages, prolongation and the damages cap are all in — and the most it is worth spending to recover it.

Page: https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-02, 4 published test vectors.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Weeks of Delay | `delayWeeks` | 6 | 6 | range 0–260 |
| Whose Delay Is It | `delayType` | The contractor's — damages run, prolongation borne | The contractor's — damages run, prolongation borne | `culpable`, `excusable`, `compensable` |
| Liquidated Damages Per Week | `liquidatedDamagesPerWeek` | 3500 | 3500 | range 0–10000000 |
| Maximum Damages | `damagesCap` | 90000 | 90000 | range 0–500000000 |
| Time-Related Preliminaries Per Week | `weeklyPrelimsRate` | 4350 | 4350 | range 0–10000000 |
| Cost of Acceleration Being Considered | `accelerationCost` | 30000 | 30000 | range 0–500000000 |
| Weeks That Acceleration Would Recover | `weeksRecovered` | 4 | 4 | range 0–260 |

- **Weeks of Delay**: How far past the completion date the job is expected to finish.
- **Whose Delay Is It**: Which of the three cases applies, because they cost completely different amounts.
- **Liquidated Damages Per Week**: The rate stated in the contract, not an estimate of the employer's loss.
- **Maximum Damages**: The total damages cap in the contract. Enter 0 if there is no cap.
- **Time-Related Preliminaries Per Week**: What the site costs to keep open for a week: staff, accommodation, services, plant standing.
- **Cost of Acceleration Being Considered**: What overtime, extra crews or additional plant would cost to recover the time.
- **Weeks That Acceleration Would Recover**: How much of the delay the spend above would actually claw back.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Cost of the delay** | $47,100 |
| Liquidated damages | $21,000 |
| Prolongation borne | $26,100 |
| Saving from recovering 4 week(s) | $31,400 |
| Cost of that acceleration | $30,000 |
| Net of accelerating | $1,400 |
| Most it is worth spending to recover those weeks | $31,400 |

### US customary

| Result | Value |
|---|---|
| **Cost of the delay** | $47,100 |
| Liquidated damages | $21,000 |
| Prolongation borne | $26,100 |
| Saving from recovering 4 week(s) | $31,400 |
| Cost of that acceleration | $30,000 |
| Net of accelerating | $1,400 |
| Most it is worth spending to recover those weeks | $31,400 |

## How it is worked out

Recovering 4 weeks saves 31400 against a spend of 30000, so accelerating is worth 1400 on these figures. Before committing, halve the weeks recovered and run it again — acceleration plans routinely deliver about half what they promise, because the constraint is usually a sequence or a lead time rather than labour hours, and a plan that only survives at the optimistic figure is not a plan.

The working the page shows, in order: Liquidated damages; Prolongation borne; Saving from recovering 4 week(s); Cost of that acceleration; Net of accelerating; Most it is worth spending to recover those weeks; then cost of the delay.

The method, derived in full:

- [Interim Valuations, Variations and the Cost of Delay](https://craftquantities.com/methodology/payment-variations-and-delay/): Why a contractor finances the retention on every project, why a change costs far more late than early, and why a skip that looks half empty can already be over its weight limit.

What this calculation does not cover:

- The contract governs. The damages rate, the cap, what counts as an excusable event and the notice a claim requires are all in it and none of them are here.
- Assumes any entitlement has been properly notified within the contractual period. Unnotified entitlement is routinely worth nothing whatever its merits.
- Damages are treated as running weekly. Some contracts state them per day or per calendar month, and a partial period then rounds differently.
- Acceleration is priced as a single figure you supply, not modelled. Lost productivity under sustained overtime and trade stacking are real and belong inside that figure.
- Consequential losses beyond the contract's damages — a lost tenancy, a missed season, a reputational cost — are outside a liquidated damages regime and outside this page.

## Sources

As the calculator cites them (sources checked 2026-09-02):

- Liquidated damages are a pre-agreed rate stated in the contract, recoverable without proof of actual loss, and in most standard forms subject to a stated maximum expressed as a percentage of the contract sum; once that maximum is reached no further damages accrue however long the delay continues
- Standard forms distinguish culpable delay (damages apply, prolongation borne by the contractor), excusable non-compensable delay such as exceptional weather (an extension of time stops damages but carries no money), and excusable compensable delay caused by the employer (an extension plus loss and expense, which recovers time-related costs)
- Loss and expense for prolongation is evaluated on the time-related preliminaries actually incurred over the extended period, not as a percentage of the contract sum, and requires notice and substantiation under every standard form

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does whose fault it is change the number so much?**

Because two separate mechanisms turn on it. Liquidated damages are the employer's remedy for late completion and stop the moment an extension of time is granted, whatever caused the delay. Prolongation — the cost of keeping the site open longer — is a real cost somebody bears, and who bears it depends on whether the delaying event carries money as well as time. A neutral event such as exceptional weather earns time but not money, so the contractor keeps the prolongation; an employer delay earns both. That is why the same six weeks can cost 47,100, 26,100, or nothing at all.

**What does the damages cap do to an acceleration decision?**

It reverses the intuition. Before the cap, every week of delay costs damages plus prolongation, so buying time back is valuable. After it, a further week costs only the prolongation, and the value of catching up drops by the damages rate overnight. On the worked figures the marginal week falls from 7,850 to 4,350 — nearly half — so an acceleration priced against the pre-cap figure overpays substantially. The saving shown here already handles it, because it prices the LAST weeks of the delay rather than the average, and those are the weeks acceleration removes first.

**Should I accelerate whenever the saving exceeds the cost?**

It is the right starting point and it is not the whole decision. Halve the weeks you expect to recover and run it again first: acceleration plans routinely deliver about half what they promise, because the binding constraint is usually a sequence, an inspection or a lead time rather than labour hours, and doubling the crew on a face that only holds one crew buys nothing. Then look at what the arithmetic cannot see — a late handover can cost a relationship, a follow-on contract, or a place on the next tender list, and none of that appears in a weekly rate.

**Where does the weekly prolongation figure come from?**

The time-related half of your preliminaries: site staff, accommodation, welfare, temporary services and plant standing on hire. Not the fixed charges — setting up and clearing away are paid once and a delay does not repeat them, so including them overstates the claim and gets it reduced as soon as anyone examines it. The Preliminaries calculator on this site produces exactly this figure and separates it for that reason.

**Can the employer deduct damages before the job finishes?**

Under most standard forms, only once the completion date has passed and only after the certificate or notice the contract requires — often a non-completion certificate followed by a written notice of intention to deduct. A deduction made without those steps is usually recoverable by the contractor, which is why the interim valuation on this site asks for deductions properly notified rather than deductions intended. The sequence matters as much as the entitlement.

## Related calculators

- [Construction Preliminaries (General Conditions) Calculator](https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/)
- [Interim Payment Valuation Calculator (Certificate Due)](https://craftquantities.com/calculators/financial-adjacent/interim-payment-valuation-calculator/)
- [Change Order Cost Calculator](https://craftquantities.com/calculators/financial-adjacent/change-order-cost-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/delay-cost-acceleration-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/delay-cost-acceleration-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `delay-cost-acceleration-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/delay-cost-acceleration-calculator.json

---
Source: https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.