# Activity Duration and Crew Size Calculator

> Turn a quantity of work and a crew's output per day into a duration in working days — or, from a deadline, into the number of crews it takes.

Page: https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-22, 4 published test vectors.

Duration of the activity: 7.5 days for Quantity of Work 600 and Crews Working at Once 2, the page's opening figures. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| What to Work Out | `mode` | How long it takes, from the crews | How long it takes, from the crews | `duration`, `crews` |
| Quantity of Work | `quantity` | 600 | 600 | range 0.01–10000000 |
| Output of One Crew per Working Day | `outputRate` | 40 | 40 | range 0.01–1000000 |
| Crews Working at Once | `crews` | 2 | 2 | range 1–100 |
| Working Days Available | `daysAvailable` | 5 | 5 | range 0.5–1000 |
| Working Days per Week | `workingWeek` | 5 — Monday to Friday | 5 — Monday to Friday | `5`, `6`, `7` |

- **What to Work Out**: The same arithmetic, solved for the duration or for the crews.
- **Quantity of Work**: How much of the work there is, in the same unit the output rate is measured in.
- **Output of One Crew per Working Day**: What one crew completes in a normal working day, in the quantity's unit.
- **Crews Working at Once**: How many crews work on the activity at the same time.
- **Working Days Available**: The working days the programme allows for the activity.
- **Working Days per Week**: Used to turn working days into weeks.

`crews` applies only when `mode` is `duration`.
`daysAvailable` applies only when `mode` is `crews`.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Duration of the activity** | 7.5 days |
| Crew-days of work | 15 crew-days |
| Whole working days to allow | 8 days |
| Weeks at 5 working days a week | 1.5 weeks |

### US customary

| Result | Value |
|---|---|
| **Duration of the activity** | 7.5 days |
| Crew-days of work | 15 crew-days |
| Whole working days to allow | 8 days |
| Weeks at 5 working days a week | 1.5 weeks |

- Confidence: medium.

## How it is worked out

The work is 15.0 crew-days; 2 crews take 7.5 working days, which a programme shows as 8. The figure is only as good as the output rate entered.

The working the page shows, in order: Crew-days of work; Whole working days to allow; Weeks at 5 working days a week; then duration of the activity.

The method, derived in full:

- [Programme Arithmetic: Durations, Float, Calendars and Learning](https://craftquantities.com/methodology/programme-arithmetic/): Why a duration is only as good as its output rate, why the critical path is the longest chain rather than the busiest, why twenty working days is four weeks, and why a repeated task gets faster by doublings.

What this calculation does not cover:

- It is only as good as the output rate, which is yours. Output falls on small quantities, awkward access, bad weather and the first days of a new crew on a new task, and none of that is in the arithmetic.
- Crews divide the time only where there is room for them to work without waiting for each other or for the trade before them.
- Working days are counted as full days. A calendar with weekends, holidays and a start date is the working-days calculator's job.

## Sources

As the calculator cites them (sources checked 2026-09-22):

- Duration from quantity and production rate, the basis of every activity estimate in a construction programme: crew-days = quantity ÷ output of one crew per working day, and working days = crew-days ÷ crews working at once
- Crew size for a fixed duration, the same relation solved the other way: crews = crew-days ÷ working days available, rounded up to whole crews

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Where does the output rate come from?**

From you. Your own records of what a crew completed on similar work are the best source, then the crew leader's estimate, then a pricing book you trust — and whichever you use, the same crew on a small, awkward job produces less than on a large, open one. This page carries no rates because an honest national figure does not exist: the output of a bricklaying gang or a drylining crew varies by a factor of two or more with the work, the access and the weather.

**Why does doubling the crews not halve the time?**

Because they need room and a supply of work. Two crews in one small room get in each other's way, and a crew that finishes its area waits for the trade before it. The arithmetic here assumes each crew works a full day at its normal output, which holds on open, repetitive work and fails in tight spaces.

**What is a crew-day?**

One crew working one day. It is the unit a quantity turns into before the number of crews is known: 15 crew-days of work is 15 days for one crew, 5 days for three, and roughly 4 days for four once the result is rounded to whole days.

**How do I turn working days into a finish date?**

With a calendar, because weekends and holidays sit between them. The working-days calculator on this site counts from a start day through the working pattern you choose, and the critical path calculator puts activities in their order once each has a duration.

## Related calculators

- [Working Days to Finish Calculator](https://craftquantities.com/calculators/financial-adjacent/working-days-finish-calculator/)
- [Critical Path and Float Calculator (CPM)](https://craftquantities.com/calculators/financial-adjacent/critical-path-float-calculator/)
- [Repetition Learning Curve Calculator (Wright and Crawford)](https://craftquantities.com/calculators/financial-adjacent/learning-curve-repetition-calculator/)
- [Labor Cost Calculator](https://craftquantities.com/calculators/financial-adjacent/labor-cost-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/activity-duration-crew-size-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/activity-duration-crew-size-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `activity-duration-crew-size-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/activity-duration-crew-size-calculator.json

---
Source: https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.