# Staircase replacement takeoff

> Replace a house's staircase with a new timber flight: dust sheets, the new flight's risers and treads checked against the reader's own rules, the handrail up the pitch and a second one where the flight takes two, spindles (balusters) counted to the IRC's landing gap, the skim on the stairwell's walls, gloss on the strings and the landing's apron, and the skip, with the temporary way up, the strip-out, any trimming of the stairwell, the floor at the landing and the foot, the boards under the flight and the floor finishes listed, never sized and never certified.

Page: https://craftquantities.com/build/staircase-replacement/ (whole-job takeoff). This is the page's Markdown copy; the HTML page is the canonical version.

## Measurements

Each length, area or volume is entered with its unit; one left out opens at the figure shown.

| Measurement | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Floor of the hall and landing protected | `floorArea` | 12 m² | 130 sq ft | m2, ft2, mm2, in2 |
| Rise, finished floor to finished floor | `rise` | 2.6 m | 8.5 ft | mm, cm, m, in, ft, yd |
| Going of each tread (its run) | `treadGoing` | 255 mm | 10 in | mm, cm, m, in, ft, yd |
| Going of the whole flight (total run) | `flightGoing` | 3.315 m | 11 ft | mm, cm, m, in, ft, yd |
| Width of the flight | `stairWidth` | 0.9 m | 3 ft | mm, cm, m, in, ft, yd |
| Handrails on the flight | `rails` | 1 | 1 | a number |
| Landing's open edge, guarded | `landingGuard` | 0.9 m | 3 ft | mm, cm, m, in, ft, yd |
| Stairwell walls patched and skimmed | `skimArea` | 8 m² | 86 sq ft | m2, ft2, mm2, in2 |
| Painted depth of a string, measured plumb | `stringDepth` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd |
| Loose waste, as a depth over the flight's plan | `wasteDepth` | 0.75 m | 2.5 ft | mm, cm, m, in, ft, yd |

- **Floor of the hall and landing protected**: The hall floor at the foot of the stair and the landing at its head, which the old flight comes down onto in pieces and the new one is carried across. The dust sheets follow it.
- **Rise, finished floor to finished floor**: From the finished floor at the foot to the finished floor of the landing, measured plumb, with the floor finishes that will be there once the job is done. The stair row divides it into equal risers, and the handrail follows it up the pitch.
- **Going of each tread (its run)**: The horizontal depth of one step from the nose of one tread to the nose of the next, as the stair maker draws it. The stair row checks it against the rules chosen; the nosing's overhang is not part of it.
- **Going of the whole flight (total run)**: On plan, from the face of the bottom riser to the face of the top one: the going of one tread times the number of treads, which is one fewer than the risers the stair row counts. The handrail and the spindles run along it, and the strings are painted along it.
- **Width of the flight**: Across the treads, wall to outside edge. The waste follows the flight's plan; where the width takes a handrail on both sides, give two rails below.
- **Handrails on the flight**: 1 for a rail on the open side over the balustrade; 2 where the flight is wide enough for the rules to ask for a rail on both sides, or the wall side is given one as well. 0 where the old rail is kept and refixed, which leaves the rail row out.
- **Landing's open edge, guarded**: The length of the landing's edge over the stairwell that takes a balustrade, newel to wall. Its apron is painted with the strings, and on the IRC option its spindles are a bay of their own. 0 where the stairwell is walled round on the landing.
- **Stairwell walls patched and skimmed**: The wall along the flight where the old wall string, its fixings and the old balustrade came off, and any other patch too large to fill: the area that is skimmed rather than filled. 0 where every mark is only filled, which leaves the skim out.
- **Painted depth of a string, measured plumb**: How far the painted face of a string reaches, measured straight up and down rather than square to its slope, with its top edge: a raked string's face is then its length on plan times this depth. The landing's apron is about the same.
- **Loose waste, as a depth over the flight's plan**: The loose volume the job makes for each square metre (square foot) of the flight's plan: the old flight and balustrade cut down, the linings, the plaster that comes off with the old wall string, and the packaging the new flight arrives in. 0.75 m (about 2 ft 6 in) over a 3.3 × 0.9 m (about 11 × 3 ft) flight is about 2.2 m³ (2.9 cubic yards).

## Build-up choices

| Choice | id | Options | Opens on (metric / US customary) |
|---|---|---|---|
| The rules the flight is checked against | `rules` | Approved Document K (England) (`adk`); IRC (US residential code) (`irc`) | `adk` / `irc` |

## Quantities on the opening figures

Worked as the takeoff page works them, each row by its own calculator.

### Metric

| Item | Quantity | Order | Calculator |
|---|---|---|---|
| Dust sheets at the foot and the head | 2 items |  | Masking and Protection Materials Calculator |
| Risers and treads, checked against the rules | 14 risers |  | Stair Rise & Run Calculator |
| Plastering: skim, in patches | 23 kg |  | Skim Coat Plaster Calculator |
| Handrail up the pitch, each rail counted | 4.63 m |  | Handrail Length Calculator |
| Painting and decorating (decoration): two paint coats, undercoat and gloss (trim enamel), on the strings and the apron | 0.651 L |  | Woodwork Paint Calculator |
| Skip (dumpster) for what comes out | 2.24 m³ |  | Skip & Dumpster Size Calculator |

### US customary

| Item | Quantity | Order | Calculator |
|---|---|---|---|
| Dust sheets at the foot and the head | 2 items |  | Masking and Protection Materials Calculator |
| Risers and treads, checked against the rules | 14 risers |  | Stair Rise & Run Calculator |
| Plastering: skim, in patches | 50.6 lb |  | Skim Coat Plaster Calculator |
| Handrail up the pitch, each rail counted | 15.3 linear ft |  | Handrail Length Calculator |
| Balusters (spindles) under the rail | 24 balusters |  | Deck Baluster Calculator |
| Balusters (spindles) along the landing's open edge | 6 balusters |  | Deck Baluster Calculator |
| Painting and decorating (decoration): two paint coats, undercoat and gloss (trim enamel), on the strings and the apron | 0.176 gal |  | Woodwork Paint Calculator |
| Skip (dumpster) for what comes out | 3.06 yd³ |  | Skip & Dumpster Size Calculator |

## Calculators it runs

- [Masking and Protection Materials Calculator](https://craftquantities.com/calculators/renovation-construction/masking-and-protection-calculator/)
- [Stair Rise & Run Calculator](https://craftquantities.com/calculators/renovation-construction/stair-calculator/)
- [Skim Coat Plaster Calculator](https://craftquantities.com/calculators/materials-quantities/skim-coat-plaster-calculator/)
- [Handrail Length Calculator](https://craftquantities.com/calculators/renovation-construction/handrail-length-calculator/)
- [Woodwork Paint Calculator](https://craftquantities.com/calculators/renovation-construction/woodwork-paint-calculator/)
- [Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- [Deck Baluster Calculator](https://craftquantities.com/calculators/renovation-construction/baluster-calculator/)

## Not counted

- The size of any trimmer, joist or beam where the stairwell is altered or partly floored over. Each is an item here; the engineer or the stair maker's designer sizes it, and nothing on this page does.
- Building control's decision on the rise, going, pitch, width and headroom: the row that checks the geometry flags a figure outside the rules chosen and says nothing of one inside them.
- Fire protection of the stair's enclosure in a house of three or more storeys: the protected route, the fire doors onto it and the linings it needs are a fire-safety design of their own.
- An understairs cupboard, storage drawers or a WC built into the space under the new flight.
- New floor finishes in the hall or upstairs beyond making good round the new footprint; the made-good carpet or boards and the strip where they meet the old finish are listed.
- Decorating beyond the stairwell's walls and the flight's woodwork: the walls, ceilings and doors of the hall and the rooms above it.
- Steel, glass, concrete and spiral stairs, and loft ladders: a timber one carried into the house in one piece is this job.
- Removing any asbestos the survey finds in the old stair's soffit or the walls round it, which is licensed or specialist work with its own programme.

## Frequently asked questions

**What does the staircase replacement takeoff give for a typical job?**

Opened at Floor of the hall and landing protected 12 m² · Rise, finished floor to finished floor 2.6 m · Going of each tread (its run) 255 mm · Going of the whole flight (total run) 3.32 m · Width of the flight 0.9 m · Handrails on the flight 1 · Landing's open edge, guarded 0.9 m · Stairwell walls patched and skimmed 8 m² · Painted depth of a string, measured plumb 300 mm · Loose waste, as a depth over the flight's plan 0.75 m, it orders: Dust sheets at the foot and the head, 2 items; Risers and treads, checked against the rules, 14 risers; Plastering: skim, in patches, 23 kg; Handrail up the pitch, each rail counted, 4.63 m; Painting and decorating (decoration): two paint coats, undercoat and gloss (trim enamel), on the strings and the apron, 0.65 L; Skip (dumpster) for what comes out, 2.24 m³. Opened at Floor of the hall and landing protected 130 sq ft · Rise, finished floor to finished floor 8.5 ft · Going of each tread (its run) 10 in · Going of the whole flight (total run) 11 ft · Width of the flight 3 ft · Handrails on the flight 1 · Landing's open edge, guarded 3 ft · Stairwell walls patched and skimmed 86 sq ft · Painted depth of a string, measured plumb 11.8 in · Loose waste, as a depth over the flight's plan 2.5 ft: Dust sheets at the foot and the head, 2 items; Risers and treads, checked against the rules, 14 risers; Plastering: skim, in patches, 50.6 lb; Handrail up the pitch, each rail counted, 15.3 linear ft; Balusters (spindles) under the rail, 24 balusters; Balusters (spindles) along the landing's open edge, 6 balusters; Painting and decorating (decoration): two paint coats, undercoat and gloss (trim enamel), on the strings and the apron, 0.18 gal; Skip (dumpster) for what comes out, 3.06 yd³. Every figure follows the dimensions you give it.

**Which calculators does the staircase replacement takeoff run?**

7 calculators, for 8 lines: Masking and Protection Materials Calculator, Stair Rise & Run Calculator, Skim Coat Plaster Calculator, Handrail Length Calculator, Deck Baluster Calculator, Woodwork Paint Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions. (US customary) / 6 calculators, one to a line: Masking and Protection Materials Calculator, Stair Rise & Run Calculator, Skim Coat Plaster Calculator, Handrail Length Calculator, Woodwork Paint Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions. (metric)

**What does the staircase replacement takeoff leave out?**

8 things, each named on this page: The size of any trimmer, joist or beam where the stairwell is altered or partly floored over; Building control's decision on the rise, going, pitch, width and headroom; Fire protection of the stair's enclosure in a house of three or more storeys; An understairs cupboard, storage drawers or a WC built into the space under the new flight; New floor finishes in the hall or upstairs beyond making good round the new footprint; the made-good carpet or boards and the strip where they meet the old finish are listed; Decorating beyond the stairwell's walls and the flight's woodwork; Steel, glass, concrete and spiral stairs, and loft ladders; Removing any asbestos the survey finds in the old stair's soffit or the walls round it, which is licensed or specialist work with its own programme.

**Can I check a quote for this job against the takeoff?**

Yes. The staircase replacement quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/takeoff/staircase-replacement` describes it; `https://api.craftquantities.com/v1/takeoff/staircase-replacement/run` works it, measurements with their units.
- MCP: the `get_takeoff` and `run_takeoff` tools at https://api.craftquantities.com/mcp with `takeoff` `staircase-replacement`.

---
Source: https://craftquantities.com/build/staircase-replacement/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.