# Solar panels (PV) with battery storage takeoff

> Fit a solar PV array on a pitched roof with a battery: the scaffold face the array is fixed from and a skip or collection for the packaging, with the network operator's (utility's) notice, the roof hooks, the rails and panels, the DC cabling, its isolation and labels, the inverter and its circuit and isolator (disconnect), the battery and any alarm the rules ask for where it stands, and the tests listed and never certified, and the roof's capacity and the array's layout flagged.

Page: https://craftquantities.com/build/solar-pv-battery/ (whole-job takeoff). This is the page's Markdown copy; the HTML page is the canonical version.

## Measurements

Each length, area or volume is entered with its unit; one left out opens at the figure shown.

| Measurement | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Scaffold along the wall below the array | `scaffoldLength` | 10 m | 33 ft | mm, cm, m, in, ft, yd |
| Height to the eaves | `eavesHeight` | 5 m | 16.5 ft | mm, cm, m, in, ft, yd |
| Weeks the scaffold stands | `scaffoldWeeks` | 2 | 2 | a number |
| Roof the panels cover | `arrayArea` | 20 m² | 220 sq ft | m2, ft2, mm2, in2 |
| Loose waste, as a depth over the panels | `wasteDepth` | 25 mm | 1 in | mm, cm, m, in, ft, yd |

- **Scaffold along the wall below the array**: The run of scaffold along the eaves below the panels, a bay past each end of the array, with the loading bay the panels come up by. 0 where the array is reached another way, from a tower on a single-storey roof or, as North American crews also work, from ladders with the crew harnessed to roof anchors; that leaves the scaffold row out.
- **Height to the eaves**: From the ground to the scaffold's top working platform, which for roof work is at or just above the eaves, with its guard rail above that.
- **Weeks the scaffold stands**: From the day it goes up to the day it is struck: the roof work of a house's array is a few days, and the weather, or a return visit to finish the mesh, can stretch it.
- **Roof the panels cover**: The panels' own area added together, from the design or the quote: a panel of a common size is about 1.7 to 2 m² (18 to 22 sq ft). The waste follows it.
- **Loose waste, as a depth over the panels**: The loose volume the job makes for each square metre (square foot) of panel: the panels' boxes and pallet, the rails' and hooks' packaging, the inverter's and the battery's cartons, rail and cable offcuts, and any tiles broken as the hooks go in. 25 mm (1 in) over 20 m² (215 sq ft) is 0.5 m³ (about 0.65 cubic yards).

## Quantities on the opening figures

Worked as the takeoff page works them, each row by its own calculator.

### Metric

| Item | Quantity | Order | Calculator |
|---|---|---|---|
| Scaffold face along the eaves | 50 m² of face |  | Scaffold Face Area and Hire Quantity Calculator |
| Skip (dumpster) or a collection for the packaging | 0.5 m³ |  | Skip & Dumpster Size Calculator |

### US customary

| Item | Quantity | Order | Calculator |
|---|---|---|---|
| Scaffold face along the eaves | 545 sq ft of face |  | Scaffold Face Area and Hire Quantity Calculator |
| Skip (dumpster) or a collection for the packaging | 0.679 yd³ |  | Skip & Dumpster Size Calculator |

## Calculators it runs

- [Scaffold Face Area and Hire Quantity Calculator](https://craftquantities.com/calculators/materials-quantities/scaffold-face-area-calculator/)
- [Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)

## Not counted

- The design of the system and its figures: how large it is, how its strings are made up and what it yields, which the designer works out. The site's sizing pages answer those figures, and none is reached here.
- A structural check of the roof and any strengthening of its rafters, which is flagged; and roof repairs found when the tiles come up, such as broken tiles, rotten battens or perished underlay.
- The network operator's or utility's approval itself, any export limit it sets and any larger supply it calls for; the notice or application is listed.
- The supplier's or utility's work on the meter, such as a smart or bidirectional meter fitted for export.
- Deciding where the energy store may stand beyond naming the rules that decide it; a smoke or heat alarm those rules ask for is listed.
- An export tariff, a grant, and the paperwork for either, beyond what the installer hands over.
- A ground-mounted rack, frames ballasted on a flat roof, solar water heating (solar thermal), and a charger for an electric vehicle: each is a job of its own.
- The scaffold's design and its inspection record, which are the scaffolder's.

## Frequently asked questions

**What does the solar panel and battery takeoff give for a typical job?**

Opened at Scaffold along the wall below the array 10 m · Height to the eaves 5 m · Weeks the scaffold stands 2 · Roof the panels cover 20 m² · Loose waste, as a depth over the panels 25 mm, it orders: Scaffold face along the eaves, 50 m² of face; Skip (dumpster) or a collection for the packaging, 0.5 m³. Opened at Scaffold along the wall below the array 33 ft · Height to the eaves 16.5 ft · Weeks the scaffold stands 2 · Roof the panels cover 220 sq ft · Loose waste, as a depth over the panels 1 in: Scaffold face along the eaves, 545 sq ft of face; Skip (dumpster) or a collection for the packaging, 0.68 yd³. Every figure follows the dimensions you give it.

**Which calculators does the solar panel and battery takeoff run?**

2 calculators, one to a line: Scaffold Face Area and Hire Quantity Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.

**What does the solar panel and battery takeoff leave out?**

8 things, each named on this page: The design of the system and its figures; A structural check of the roof and any strengthening of its rafters, which is flagged; and roof repairs found when the tiles come up, such as broken tiles, rotten battens or perished underlay; The network operator's or utility's approval itself, any export limit it sets and any larger supply it calls for; the notice or application is listed; The supplier's or utility's work on the meter, such as a smart or bidirectional meter fitted for export; Deciding where the energy store may stand beyond naming the rules that decide it; a smoke or heat alarm those rules ask for is listed; An export tariff, a grant, and the paperwork for either, beyond what the installer hands over; A ground-mounted rack, frames ballasted on a flat roof, solar water heating (solar thermal), and a charger for an electric vehicle; The scaffold's design and its inspection record, which are the scaffolder's.

**Can I check a quote for this job against the takeoff?**

Yes. The solar panel and battery quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/takeoff/solar-pv-battery` describes it; `https://api.craftquantities.com/v1/takeoff/solar-pv-battery/run` works it, measurements with their units.
- MCP: the `get_takeoff` and `run_takeoff` tools at https://api.craftquantities.com/mcp with `takeoff` `solar-pv-battery`.

---
Source: https://craftquantities.com/build/solar-pv-battery/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.