  "version": "v1",
  "source": "https://craftquantities.com",
  "licence": "CC BY 4.0",
  "licenceUrl": "https://creativecommons.org/licenses/by/4.0/",
  "attribution": "Craft Quantities — craftquantities.com",
  "documentation": "https://craftquantities.com/api/",
  "versioning": "Fields are added, never removed or repurposed, within a version. A breaking change becomes /api/v2/ and v1 keeps being built.",
  "slug": "preliminaries-cost-calculator",
  "category": "financial-adjacent",
  "title": "Construction Preliminaries (General Conditions) Calculator",
  "description": "Add up preliminaries (general conditions) from your own weekly and one-off figures: fixed, time-related and value-related, and what a week of delay adds.",
  "url": "https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/",
  "json": "https://craftquantities.com/api/v1/calculators/preliminaries-cost-calculator.json",
  "inputCount": 10,
  "testCaseCount": 3,
  "sourceCount": 3,
  "lastVerified": "2026-09-02",
  "citation": {
    "author": "Craft Quantities",
    "title": "Construction Preliminaries (General Conditions) Calculator",
    "version": "1.0.0",
    "sourcesChecked": "2026-09-02",
    "url": "https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/",
    "accessDate": null,
    "accessDateNote": "Add the date you retrieved this. It is deliberately absent: a static file cannot know when you read it, and the build date would be wrong.",
    "permanentVersionedUrl": null,
    "permanentVersionedUrlNote": "Not offered. This site keeps no archive of previous builds, so any such URL would resolve to the current page or to nothing. The version and sourcesChecked fields identify the calculation instead.",
    "formats": {
      "plain": "Craft Quantities. Construction Preliminaries (General Conditions) Calculator. Version 1.0.0. Sources checked 2026-09-02. https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/",
      "apa": "Craft Quantities. (2026). Construction Preliminaries (General Conditions) Calculator (Version 1.0.0) [Web calculator]. Retrieved from https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/",
      "harvard": "Craft Quantities (2026) Construction Preliminaries (General Conditions) Calculator (Version 1.0.0). Available at: https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/",
      "bibtex": "@misc{craftquantities-calculators-financial-adjacent-preliminaries-cost-calculator,\n  author       = {{Craft Quantities}},\n  title        = {Construction Preliminaries (General Conditions) Calculator},\n  version      = {1.0.0},\n  year         = {2026},\n  howpublished = {\\url{https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/}},\n}"
    }
  },
  "inputs": [
    {
      "id": "programmeWeeks",
      "label": "Programme Duration",
      "type": "number",
      "defaultValue": 26,
      "min": 1,
      "max": 260,
      "step": 1,
      "help": "The contract period in weeks, from possession of the site to practical completion."
    },
    {
      "id": "siteStaffCount",
      "label": "Full-Time Site Staff",
      "type": "number",
      "defaultValue": 2,
      "min": 0,
      "max": 50,
      "step": 1,
      "help": "People on site full-time whose cost is not in any trade rate."
    },
    {
      "id": "siteStaffWeeklyCost",
      "label": "Cost Per Person Per Week",
      "type": "number",
      "defaultValue": "",
      "min": 0,
      "max": 20000,
      "step": 50,
      "help": "All-in weekly cost of one member of site staff.",
      "money": {
        "role": "rate",
        "appliesTo": "siteStaffCount"
      }
    },
    {
      "id": "accommodationWeekly",
      "label": "Accommodation and Welfare Per Week",
      "type": "number",
      "defaultValue": "",
      "min": 0,
      "max": 50000,
      "step": 25,
      "help": "Weekly hire of offices, canteen, drying room, toilets and stores.",
      "money": {
        "role": "rate"
      }
    },
    {
      "id": "servicesWeekly",
      "label": "Temporary Services and Waste Per Week",
      "type": "number",
      "defaultValue": "",
      "min": 0,
      "max": 50000,
      "step": 25,
      "help": "Power, water, lighting, telecoms and skips, per week.",
      "money": {
        "role": "rate"
      }
    },
    {
      "id": "plantStandingWeekly",
      "label": "Plant Standing Per Week",
      "type": "number",
      "defaultValue": "",
      "min": 0,
      "max": 100000,
      "step": 50,
      "help": "Weekly hire of plant that stands on site rather than belonging to a trade.",
      "money": {
        "role": "rate"
      }
    },
    {
      "id": "setupCost",
      "label": "Setting Up (One-Off)",
      "type": "number",
      "defaultValue": 12000,
      "min": 0,
      "max": 5000000,
      "step": 500,
      "help": "Mobilisation: hoarding, gates, signage, hardstanding, first connections.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "removalCost",
      "label": "Clearing Away (One-Off)",
      "type": "number",
      "defaultValue": 6000,
      "min": 0,
      "max": 5000000,
      "step": 500,
      "help": "Demobilisation: removing everything and making the ground good.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "contractSum",
      "label": "Contract Sum",
      "type": "number",
      "defaultValue": 1000000,
      "min": 0,
      "max": 500000000,
      "step": 10000,
      "help": "The contract value, used for the value-related items and the percentage check.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "insuranceAndBondPercent",
      "label": "Insurance and Bonds",
      "type": "number",
      "defaultValue": 1.2,
      "min": 0,
      "max": 10,
      "step": 0.1,
      "help": "Contract works insurance, liability cover and any bond, as a percent of the sum."
    }
  ],
  "sources": [
    {
      "label": "Standard methods of measurement (NRM 1/2 in the UK, and the general conditions divisions of CSI MasterFormat 01 in North America) classify site-running costs as fixed charges, time-related charges and value-related charges — the split that lets a change in programme be priced separately from a change in scope"
    },
    {
      "label": "Preliminaries on a main building contract commonly run 8-15% of the contract sum, higher on small, short or constrained sites and lower on large repetitive ones, because the fixed element is spread over more value"
    },
    {
      "label": "The time-related total divided by the programme duration is the weekly prolongation rate — the basis on which loss and expense is evaluated when an extension of time is granted. It excludes fixed charges, which are not incurred again by a delay"
    }
  ],
  "testCases": [
    {
      "name": "26-week job, two staff, ordinary weekly items",
      "inputs": {
        "programmeWeeks": 26,
        "siteStaffCount": 2,
        "siteStaffWeeklyCost": 1400,
        "accommodationWeekly": 450,
        "servicesWeekly": 300,
        "plantStandingWeekly": 800,
        "setupCost": 12000,
        "removalCost": 6000,
        "contractSum": 900000,
        "insuranceAndBondPercent": 1.2
      },
      "expected": 141900,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "low",
      "steps": [
        {
          "label": "Time-related, per week",
          "value": 4350,
          "unit": "per week"
        },
        {
          "label": "Time-related over 26 weeks",
          "value": 113100,
          "unit": "currency"
        },
        {
          "label": "Fixed (setting up and clearing away)",
          "value": 18000,
          "unit": "currency"
        },
        {
          "label": "Value-related (insurance and bonds)",
          "value": 10800,
          "unit": "currency"
        },
        {
          "label": "Share of the contract sum",
          "value": 15.77,
          "unit": "%"
        },
        {
          "label": "Cost of one week's delay",
          "value": 4350,
          "unit": "per week"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "the weekly rate excludes the fixed charges a delay does not repeat",
      "inputs": {
        "programmeWeeks": 52,
        "siteStaffCount": 2,
        "siteStaffWeeklyCost": 1400,
        "accommodationWeekly": 450,
        "servicesWeekly": 300,
        "plantStandingWeekly": 800,
        "setupCost": 12000,
        "removalCost": 6000,
        "contractSum": 1800000,
        "insuranceAndBondPercent": 1.2
      },
      "expected": 265800,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "medium",
      "steps": [
        {
          "label": "Time-related, per week",
          "value": 4350,
          "unit": "per week"
        },
        {
          "label": "Time-related over 52 weeks",
          "value": 226200,
          "unit": "currency"
        },
        {
          "label": "Fixed (setting up and clearing away)",
          "value": 18000,
          "unit": "currency"
        },
        {
          "label": "Value-related (insurance and bonds)",
          "value": 21600,
          "unit": "currency"
        },
        {
          "label": "Share of the contract sum",
          "value": 14.77,
          "unit": "%"
        },
        {
          "label": "Cost of one week's delay",
          "value": 4350,
          "unit": "per week"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "a bare site with no staff still costs its setting up",
      "inputs": {
        "programmeWeeks": 4,
        "siteStaffCount": 0,
        "siteStaffWeeklyCost": 1400,
        "accommodationWeekly": 0,
        "servicesWeekly": 0,
        "plantStandingWeekly": 0,
        "setupCost": 3000,
        "removalCost": 1500,
        "contractSum": 40000,
        "insuranceAndBondPercent": 1
      },
      "expected": 4900,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "medium",
      "steps": [
        {
          "label": "Time-related, per week",
          "value": 0,
          "unit": "per week"
        },
        {
          "label": "Time-related over 4 weeks",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Fixed (setting up and clearing away)",
          "value": 4500,
          "unit": "currency"
        },
        {
          "label": "Value-related (insurance and bonds)",
          "value": 400,
          "unit": "currency"
        },
        {
          "label": "Share of the contract sum",
          "value": 12.25,
          "unit": "%"
        },
        {
          "label": "Cost of one week's delay",
          "value": 0,
          "unit": "per week"
        }
      ],
      "basis": "ambiguous"
    }
  ]
}