  "slug": "earned-value-management-calculator",
  "category": "financial-adjacent",
  "title": "Earned Value Management (EVM) Calculator",
  "description": "CPI, SPI, variances and a forecast at completion from planned value, earned value and actual cost.",
  "url": "https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/",
  "json": "https://craftquantities.com/api/v1/calculators/earned-value-management-calculator.json",
  "inputCount": 4,
  "testCaseCount": 4,
  "sourceCount": 2,
  "lastVerified": "2026-09-06",
  "citation": {
    "author": "Craft Quantities",
    "title": "Earned Value Management (EVM) Calculator",
    "version": "1.0.1",
    "sourcesChecked": "2026-09-06",
    "url": "https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/",
    "accessDate": null,
    "accessDateNote": "Add the date you retrieved this. It is deliberately absent: a static file cannot know when you read it, and the build date would be wrong.",
    "permanentVersionedUrl": null,
    "permanentVersionedUrlNote": "Not offered. This site keeps no archive of previous builds, so any such URL would resolve to the current page or to nothing. The version and sourcesChecked fields identify the calculation instead.",
    "formats": {
      "plain": "Craft Quantities. Earned Value Management (EVM) Calculator. Version 1.0.1. Sources checked 2026-09-06. https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/",
      "apa": "Craft Quantities. (2026). Earned Value Management (EVM) Calculator (Version 1.0.1) [Web calculator]. Retrieved from https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/",
      "harvard": "Craft Quantities (2026) Earned Value Management (EVM) Calculator (Version 1.0.1). Available at: https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/",
      "bibtex": "@misc{craftquantities-calculators-financial-adjacent-earned-value-management-calculator,\n  author       = {{Craft Quantities}},\n  title        = {Earned Value Management (EVM) Calculator},\n  version      = {1.0.1},\n  year         = {2026},\n  howpublished = {\\url{https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/}},\n}"
    }
  },
  "inputs": [
    {
      "id": "bac",
      "label": "Budget at completion (BAC)",
      "type": "number",
      "defaultValue": 1000000,
      "min": 1,
      "max": 10000000000,
      "step": 1000,
      "help": "Total authorised budget for the work.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "pv",
      "label": "Planned value (PV)",
      "type": "number",
      "defaultValue": 400000,
      "min": 0,
      "max": 10000000000,
      "step": 1000,
      "help": "Budgeted cost of work scheduled to date.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "ev",
      "label": "Earned value (EV)",
      "type": "number",
      "defaultValue": 360000,
      "min": 0,
      "max": 10000000000,
      "step": 1000,
      "help": "Budgeted cost of work actually completed.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "ac",
      "label": "Actual cost (AC)",
      "type": "number",
      "defaultValue": 420000,
      "min": 0,
      "max": 10000000000,
      "step": 1000,
      "help": "What has actually been spent on that work.",
      "money": {
        "role": "amount"
      }
    }
  ],
  "sources": [
    {
      "label": "PMBOK earned value definitions: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV"
    },
    {
      "label": "EAC = BAC ÷ CPI where current cost performance is expected to continue; the most commonly used of several sanctioned formulas"
    }
  ],
  "testCases": [
    {
      "name": "Over budget and behind schedule",
      "inputs": {
        "bac": 1000000,
        "pv": 400000,
        "ev": 360000,
        "ac": 420000
      },
      "expected": 1166666.67,
      "toleranceDecimalPlaces": -4,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Cost performance index (CPI)",
          "value": 0.8571428571428571
        },
        {
          "label": "Schedule performance index (SPI)",
          "value": 0.9
        },
        {
          "label": "Cost variance (CV)",
          "value": -60000,
          "unit": "currency"
        },
        {
          "label": "Schedule variance (SV)",
          "value": -40000,
          "unit": "currency"
        },
        {
          "label": "Variance at completion (VAC)",
          "value": -166666.66666666674,
          "unit": "currency"
        },
        {
          "label": "Estimate to complete (ETC)",
          "value": 746666.6666666667,
          "unit": "currency"
        },
        {
          "label": "To-complete performance index (TCPI)",
          "value": 1.103448275862069
        },
        {
          "label": "Percent complete",
          "value": 36,
          "unit": "%"
        },
        {
          "label": "Percent spent",
          "value": 42,
          "unit": "%"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "Exactly on plan gives EAC equal to BAC",
      "inputs": {
        "bac": 1000000,
        "pv": 400000,
        "ev": 400000,
        "ac": 400000
      },
      "expected": 1000000,
      "toleranceDecimalPlaces": -4,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Cost performance index (CPI)",
          "value": 1
        },
        {
          "label": "Schedule performance index (SPI)",
          "value": 1
        },
        {
          "label": "Cost variance (CV)",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Schedule variance (SV)",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Variance at completion (VAC)",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Estimate to complete (ETC)",
          "value": 600000,
          "unit": "currency"
        },
        {
          "label": "To-complete performance index (TCPI)",
          "value": 1
        },
        {
          "label": "Percent complete",
          "value": 40,
          "unit": "%"
        },
        {
          "label": "Percent spent",
          "value": 40,
          "unit": "%"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "Running under cost forecasts a saving",
      "inputs": {
        "bac": 1000000,
        "pv": 400000,
        "ev": 400000,
        "ac": 350000
      },
      "expected": 875000,
      "toleranceDecimalPlaces": -4,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Cost performance index (CPI)",
          "value": 1.1428571428571428
        },
        {
          "label": "Schedule performance index (SPI)",
          "value": 1
        },
        {
          "label": "Cost variance (CV)",
          "value": 50000,
          "unit": "currency"
        },
        {
          "label": "Schedule variance (SV)",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Variance at completion (VAC)",
          "value": 125000,
          "unit": "currency"
        },
        {
          "label": "Estimate to complete (ETC)",
          "value": 525000,
          "unit": "currency"
        },
        {
          "label": "To-complete performance index (TCPI)",
          "value": 0.9230769230769231
        },
        {
          "label": "Percent complete",
          "value": 40,
          "unit": "%"
        },
        {
          "label": "Percent spent",
          "value": 35,
          "unit": "%"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "Severe overrun",
      "inputs": {
        "bac": 1000000,
        "pv": 500000,
        "ev": 300000,
        "ac": 600000
      },
      "expected": 2000000,
      "toleranceDecimalPlaces": -4,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Cost performance index (CPI)",
          "value": 0.5
        },
        {
          "label": "Schedule performance index (SPI)",
          "value": 0.6
        },
        {
          "label": "Cost variance (CV)",
          "value": -300000,
          "unit": "currency"
        },
        {
          "label": "Schedule variance (SV)",
          "value": -200000,
          "unit": "currency"
        },
        {
          "label": "Variance at completion (VAC)",
          "value": -1000000,
          "unit": "currency"
        },
        {
          "label": "Estimate to complete (ETC)",
          "value": 1400000,
          "unit": "currency"
        },
        {
          "label": "To-complete performance index (TCPI)",
          "value": 1.75
        },
        {
          "label": "Percent complete",
          "value": 30,
          "unit": "%"
        },
        {
          "label": "Percent spent",
          "value": 60,
          "unit": "%"
        }
      ],
      "basis": "ambiguous"
    }
  ]
}