  "version": "v1",
  "source": "https://craftquantities.com",
  "licence": "CC BY 4.0",
  "licenceUrl": "https://creativecommons.org/licenses/by/4.0/",
  "attribution": "Craft Quantities — craftquantities.com",
  "documentation": "https://craftquantities.com/api/",
  "versioning": "Fields are added, never removed or repurposed, within a version. A breaking change becomes /api/v2/ and v1 keeps being built.",
  "slug": "delay-cost-acceleration-calculator",
  "category": "financial-adjacent",
  "title": "Delay Cost and Acceleration Break-Even Calculator",
  "description": "What a week of delay costs once damages, prolongation and the damages cap are all in — and the most it is worth spending to recover it.",
  "url": "https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/",
  "json": "https://craftquantities.com/api/v1/calculators/delay-cost-acceleration-calculator.json",
  "inputCount": 7,
  "testCaseCount": 4,
  "sourceCount": 3,
  "lastVerified": "2026-09-02",
  "citation": {
    "author": "Craft Quantities",
    "title": "Delay Cost and Acceleration Break-Even Calculator",
    "version": "1.0.0",
    "sourcesChecked": "2026-09-02",
    "url": "https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/",
    "accessDate": null,
    "accessDateNote": "Add the date you retrieved this. It is deliberately absent: a static file cannot know when you read it, and the build date would be wrong.",
    "permanentVersionedUrl": null,
    "permanentVersionedUrlNote": "Not offered. This site keeps no archive of previous builds, so any such URL would resolve to the current page or to nothing. The version and sourcesChecked fields identify the calculation instead.",
    "formats": {
      "plain": "Craft Quantities. Delay Cost and Acceleration Break-Even Calculator. Version 1.0.0. Sources checked 2026-09-02. https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/",
      "apa": "Craft Quantities. (2026). Delay Cost and Acceleration Break-Even Calculator (Version 1.0.0) [Web calculator]. Retrieved from https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/",
      "harvard": "Craft Quantities (2026) Delay Cost and Acceleration Break-Even Calculator (Version 1.0.0). Available at: https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/",
      "bibtex": "@misc{craftquantities-calculators-financial-adjacent-delay-cost-acceleration-calculator,\n  author       = {{Craft Quantities}},\n  title        = {Delay Cost and Acceleration Break-Even Calculator},\n  version      = {1.0.0},\n  year         = {2026},\n  howpublished = {\\url{https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/}},\n}"
    }
  },
  "inputs": [
    {
      "id": "delayWeeks",
      "label": "Weeks of Delay",
      "type": "number",
      "defaultValue": 6,
      "min": 0,
      "max": 260,
      "step": 1,
      "help": "How far past the completion date the job is expected to finish."
    },
    {
      "id": "delayType",
      "label": "Whose Delay Is It",
      "type": "select",
      "defaultValue": "culpable",
      "options": [
        {
          "value": "culpable",
          "label": "The contractor's — damages run, prolongation borne"
        },
        {
          "value": "excusable",
          "label": "Neutral event with an extension — no damages, prolongation borne"
        },
        {
          "value": "compensable",
          "label": "The employer's — extension and loss and expense"
        }
      ],
      "help": "Which of the three cases applies, because they cost completely different amounts."
    },
    {
      "id": "liquidatedDamagesPerWeek",
      "label": "Liquidated Damages Per Week",
      "type": "number",
      "defaultValue": 3500,
      "min": 0,
      "max": 10000000,
      "step": 100,
      "help": "The rate stated in the contract, not an estimate of the employer's loss.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "damagesCap",
      "label": "Maximum Damages",
      "type": "number",
      "defaultValue": 90000,
      "min": 0,
      "max": 500000000,
      "step": 1000,
      "help": "The total damages cap in the contract. Enter 0 if there is no cap.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "weeklyPrelimsRate",
      "label": "Time-Related Preliminaries Per Week",
      "type": "number",
      "defaultValue": 4350,
      "min": 0,
      "max": 10000000,
      "step": 50,
      "help": "What the site costs to keep open for a week: staff, accommodation, services, plant standing.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "accelerationCost",
      "label": "Cost of Acceleration Being Considered",
      "type": "number",
      "defaultValue": 30000,
      "min": 0,
      "max": 500000000,
      "step": 500,
      "help": "What overtime, extra crews or additional plant would cost to recover the time.",
      "money": {
        "role": "amount"
      }
    },
    {
      "id": "weeksRecovered",
      "label": "Weeks That Acceleration Would Recover",
      "type": "number",
      "defaultValue": 4,
      "min": 0,
      "max": 260,
      "step": 1,
      "help": "How much of the delay the spend above would actually claw back."
    }
  ],
  "sources": [
    {
      "label": "Liquidated damages are a pre-agreed rate stated in the contract, recoverable without proof of actual loss, and in most standard forms subject to a stated maximum expressed as a percentage of the contract sum; once that maximum is reached no further damages accrue however long the delay continues"
    },
    {
      "label": "Standard forms distinguish culpable delay (damages apply, prolongation borne by the contractor), excusable non-compensable delay such as exceptional weather (an extension of time stops damages but carries no money), and excusable compensable delay caused by the employer (an extension plus loss and expense, which recovers time-related costs)"
    },
    {
      "label": "Loss and expense for prolongation is evaluated on the time-related preliminaries actually incurred over the extended period, not as a percentage of the contract sum, and requires notice and substantiation under every standard form"
    }
  ],
  "testCases": [
    {
      "name": "six culpable weeks, inside the damages cap",
      "inputs": {
        "delayWeeks": 6,
        "delayType": "culpable",
        "liquidatedDamagesPerWeek": 3500,
        "damagesCap": 90000,
        "weeklyPrelimsRate": 4350,
        "accelerationCost": 30000,
        "weeksRecovered": 4
      },
      "expected": 47100,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Liquidated damages",
          "value": 21000,
          "unit": "currency"
        },
        {
          "label": "Prolongation borne",
          "value": 26100,
          "unit": "currency"
        },
        {
          "label": "Saving from recovering 4 week(s)",
          "value": 31400,
          "unit": "currency"
        },
        {
          "label": "Cost of that acceleration",
          "value": 30000,
          "unit": "currency"
        },
        {
          "label": "Net of accelerating",
          "value": 1400,
          "unit": "currency"
        },
        {
          "label": "Most it is worth spending to recover those weeks",
          "value": 31400,
          "unit": "currency"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "the cap bites, so the delay costs far less than the weekly rate suggests",
      "inputs": {
        "delayWeeks": 40,
        "delayType": "culpable",
        "liquidatedDamagesPerWeek": 3500,
        "damagesCap": 90000,
        "weeklyPrelimsRate": 4350,
        "accelerationCost": 30000,
        "weeksRecovered": 4
      },
      "expected": 264000,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Liquidated damages",
          "value": 90000,
          "unit": "currency"
        },
        {
          "label": "Prolongation borne",
          "value": 174000,
          "unit": "currency"
        },
        {
          "label": "Saving from recovering 4 week(s)",
          "value": 17400,
          "unit": "currency"
        },
        {
          "label": "Cost of that acceleration",
          "value": 30000,
          "unit": "currency"
        },
        {
          "label": "Net of accelerating",
          "value": -12600,
          "unit": "currency"
        },
        {
          "label": "Most it is worth spending to recover those weeks",
          "value": 17400,
          "unit": "currency"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "a neutral event: an extension stops the damages, the prolongation stays",
      "inputs": {
        "delayWeeks": 6,
        "delayType": "excusable",
        "liquidatedDamagesPerWeek": 3500,
        "damagesCap": 90000,
        "weeklyPrelimsRate": 4350,
        "accelerationCost": 30000,
        "weeksRecovered": 4
      },
      "expected": 26100,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Liquidated damages",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Prolongation borne",
          "value": 26100,
          "unit": "currency"
        },
        {
          "label": "Saving from recovering 4 week(s)",
          "value": 17400,
          "unit": "currency"
        },
        {
          "label": "Cost of that acceleration",
          "value": 30000,
          "unit": "currency"
        },
        {
          "label": "Net of accelerating",
          "value": -12600,
          "unit": "currency"
        },
        {
          "label": "Most it is worth spending to recover those weeks",
          "value": 17400,
          "unit": "currency"
        }
      ],
      "basis": "ambiguous"
    },
    {
      "name": "an employer delay properly notified costs the contractor nothing",
      "inputs": {
        "delayWeeks": 6,
        "delayType": "compensable",
        "liquidatedDamagesPerWeek": 3500,
        "damagesCap": 90000,
        "weeklyPrelimsRate": 4350,
        "accelerationCost": 30000,
        "weeksRecovered": 4
      },
      "expected": 0,
      "toleranceDecimalPlaces": 0,
      "unit": "currency",
      "confidence": "high",
      "steps": [
        {
          "label": "Liquidated damages",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Prolongation borne",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Saving from recovering 4 week(s)",
          "value": 0,
          "unit": "currency"
        },
        {
          "label": "Cost of that acceleration",
          "value": 30000,
          "unit": "currency"
        },
        {
          "label": "Net of accelerating",
          "value": -30000,
          "unit": "currency"
        },
        {
          "label": "Most it is worth spending to recover those weeks",
          "value": 0,
          "unit": "currency"
        }
      ],
      "basis": "ambiguous"
    }
  ]
}