  "version": "v1",
  "source": "https://craftquantities.com",
  "licence": "CC BY 4.0",
  "licenceUrl": "https://creativecommons.org/licenses/by/4.0/",
  "attribution": "Craft Quantities — craftquantities.com",
  "documentation": "https://craftquantities.com/api/",
  "versioning": "Fields are added, never removed or repurposed, within a version. A breaking change becomes /api/v2/ and v1 keeps being built.",
  "slug": "activity-duration-crew-size-calculator",
  "category": "financial-adjacent",
  "title": "Activity Duration and Crew Size Calculator",
  "description": "Turn a quantity of work and a crew's output per day into a duration in working days — or, from a deadline, into the number of crews it takes.",
  "url": "https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/",
  "json": "https://craftquantities.com/api/v1/calculators/activity-duration-crew-size-calculator.json",
  "inputCount": 6,
  "testCaseCount": 4,
  "sourceCount": 2,
  "lastVerified": "2026-09-22",
  "citation": {
    "author": "Craft Quantities",
    "title": "Activity Duration and Crew Size Calculator",
    "version": "1.0.0",
    "sourcesChecked": "2026-09-22",
    "url": "https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/",
    "accessDate": null,
    "accessDateNote": "Add the date you retrieved this. It is deliberately absent: a static file cannot know when you read it, and the build date would be wrong.",
    "permanentVersionedUrl": null,
    "permanentVersionedUrlNote": "Not offered. This site keeps no archive of previous builds, so any such URL would resolve to the current page or to nothing. The version and sourcesChecked fields identify the calculation instead.",
    "formats": {
      "plain": "Craft Quantities. Activity Duration and Crew Size Calculator. Version 1.0.0. Sources checked 2026-09-22. https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/",
      "apa": "Craft Quantities. (2026). Activity Duration and Crew Size Calculator (Version 1.0.0) [Web calculator]. Retrieved from https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/",
      "harvard": "Craft Quantities (2026) Activity Duration and Crew Size Calculator (Version 1.0.0). Available at: https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/",
      "bibtex": "@misc{craftquantities-calculators-financial-adjacent-activity-duration-crew-size-calculator,\n  author       = {{Craft Quantities}},\n  title        = {Activity Duration and Crew Size Calculator},\n  version      = {1.0.0},\n  year         = {2026},\n  howpublished = {\\url{https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/}},\n}"
    }
  },
  "inputs": [
    {
      "id": "mode",
      "label": "What to Work Out",
      "type": "select",
      "defaultValue": "duration",
      "options": [
        {
          "value": "duration",
          "label": "How long it takes, from the crews"
        },
        {
          "value": "crews",
          "label": "How many crews, from the deadline"
        }
      ],
      "help": "The same arithmetic, solved for the duration or for the crews."
    },
    {
      "id": "quantity",
      "label": "Quantity of Work",
      "type": "number",
      "defaultValue": 600,
      "min": 0.01,
      "max": 10000000,
      "step": 1,
      "help": "How much of the work there is, in the same unit the output rate is measured in."
    },
    {
      "id": "outputRate",
      "label": "Output of One Crew per Working Day",
      "type": "number",
      "defaultValue": 40,
      "min": 0.01,
      "max": 1000000,
      "step": 0.5,
      "help": "What one crew completes in a normal working day, in the quantity's unit."
    },
    {
      "id": "crews",
      "label": "Crews Working at Once",
      "type": "number",
      "defaultValue": 2,
      "min": 1,
      "max": 100,
      "step": 1,
      "help": "How many crews work on the activity at the same time."
    },
    {
      "id": "daysAvailable",
      "label": "Working Days Available",
      "type": "number",
      "defaultValue": 5,
      "min": 0.5,
      "max": 1000,
      "step": 0.5,
      "help": "The working days the programme allows for the activity."
    },
    {
      "id": "workingWeek",
      "label": "Working Days per Week",
      "type": "select",
      "defaultValue": "5",
      "options": [
        {
          "value": "5",
          "label": "5 — Monday to Friday"
        },
        {
          "value": "6",
          "label": "6 — Monday to Saturday"
        },
        {
          "value": "7",
          "label": "7 — every day"
        }
      ],
      "help": "Used to turn working days into weeks."
    }
  ],
  "sources": [
    {
      "label": "Duration from quantity and production rate, the basis of every activity estimate in a construction programme: crew-days = quantity ÷ output of one crew per working day, and working days = crew-days ÷ crews working at once"
    },
    {
      "label": "Crew size for a fixed duration, the same relation solved the other way: crews = crew-days ÷ working days available, rounded up to whole crews"
    }
  ],
  "testCases": [
    {
      "name": "The defaults: 600 at 40 a crew-day, two crews",
      "inputs": {
        "mode": "duration",
        "quantity": 600,
        "outputRate": 40,
        "crews": 2,
        "daysAvailable": 5,
        "workingWeek": "5"
      },
      "expected": 7.5,
      "toleranceDecimalPlaces": 4,
      "unit": "days",
      "confidence": "medium",
      "steps": [
        {
          "label": "Crew-days of work",
          "value": 15,
          "unit": "crew-days"
        },
        {
          "label": "Whole working days to allow",
          "value": 8,
          "unit": "days"
        },
        {
          "label": "Weeks at 5 working days a week",
          "value": 1.5,
          "unit": "weeks"
        }
      ],
      "basis": "cited",
      "sourceIndex": 0
    },
    {
      "name": "Three crews on 1,250 at 55",
      "inputs": {
        "mode": "duration",
        "quantity": 1250,
        "outputRate": 55,
        "crews": 3,
        "daysAvailable": 5,
        "workingWeek": "6"
      },
      "expected": 7.575758,
      "toleranceDecimalPlaces": 4,
      "unit": "days",
      "confidence": "medium",
      "steps": [
        {
          "label": "Crew-days of work",
          "value": 22.727272727272727,
          "unit": "crew-days"
        },
        {
          "label": "Whole working days to allow",
          "value": 8,
          "unit": "days"
        },
        {
          "label": "Weeks at 6 working days a week",
          "value": 1.2626262626262625,
          "unit": "weeks"
        }
      ],
      "basis": "cited",
      "sourceIndex": 0
    },
    {
      "name": "Crews for a five-day deadline",
      "inputs": {
        "mode": "crews",
        "quantity": 600,
        "outputRate": 40,
        "crews": 2,
        "daysAvailable": 5,
        "workingWeek": "5"
      },
      "expected": 3,
      "toleranceDecimalPlaces": 0,
      "unit": "crews",
      "confidence": "medium",
      "steps": [
        {
          "label": "Crew-days of work",
          "value": 15,
          "unit": "crew-days"
        },
        {
          "label": "Crews needed, before rounding up",
          "value": 3,
          "unit": "crews"
        },
        {
          "label": "Working days those crews take",
          "value": 5,
          "unit": "days"
        },
        {
          "label": "Working days to spare",
          "value": 0,
          "unit": "days"
        }
      ],
      "basis": "cited",
      "sourceIndex": 1
    },
    {
      "name": "Crews round up to whole crews",
      "inputs": {
        "mode": "crews",
        "quantity": 1250,
        "outputRate": 55,
        "crews": 2,
        "daysAvailable": 10,
        "workingWeek": "7"
      },
      "expected": 3,
      "toleranceDecimalPlaces": 0,
      "unit": "crews",
      "confidence": "medium",
      "steps": [
        {
          "label": "Crew-days of work",
          "value": 22.727272727272727,
          "unit": "crew-days"
        },
        {
          "label": "Crews needed, before rounding up",
          "value": 2.2727272727272725,
          "unit": "crews"
        },
        {
          "label": "Working days those crews take",
          "value": 7.575757575757575,
          "unit": "days"
        },
        {
          "label": "Working days to spare",
          "value": 2.4242424242424248,
          "unit": "days"
        }
      ],
      "basis": "cited",
      "sourceIndex": 1
    }
  ]
}